Thursday 15 August 2013

Wednesday's Pour

Yesterday was a big day on the Parkview project.  The street was closed to allow a big concrete pump truck to set up to place concrete in the next two foundations and floors in unit 3.  The floors will be heated by hot water circulating through a series of looped plastic embedded in the concrete.  yesterday the pumper delivered concrete through a window on each level where it was spread, levelled and then power trowelled.  In a couple of weeks it will be honed, but even today they look fantastic.

The next operation was placing the concrete in the Insulated Concrete Forms (ICF)  forms for unit 2 and 5's foundations.  This was a little nerve-wracking as they are at least 10 feet high and if done to quickly could potentially burst open.  They were well braced and by placing a 4 foot lift first and letting it set a little, the forms were able to accept the second, top-up lift.