Windows at Parkview !

The window frames arrived last week are installed in the first unit.  There is plastic sheeting on the outside as with these high quality commercial steel frames the glass is installed in place.  This, at least made lifting the large sizes them up along the outside wall practical. These rooms will look east towards PArliament.  There is a great view of the city skyline and Peace Tower through the enormous sliding doors up in the penthouse.

Drywall is mostly complete, except for some interior walls.  The first floor, which will be the kitchen and living space is not yet primed, but with windows across the entire end wall and 10 foot high ceilings it will be a very bright space.

The next stage will be to install the heating pipes and pour the concrete floors. Then interior walls, cabinets and such can be installed.